POWER COLUMN Q4 2022

 

In the period under review, ZPC produced 1,719GWh, falling short of its quarterly goal of 2,490GWh  by 30.96%  due to numerous forced outages.  The power generation utility missed its 9,111GWh annual energy sent out target for 2022 by 7.29%.

Kariba South Power Station was allocated 22.5Bm3 of water by Zambezi River Authority (ZRA) for power generation in 2022 which is equivalent to an average generation capacity of 606MW.  However, due to the incessant breakdown of the aged units at the Hwange Power Station and lack of foreign currency to import electricity, Kariba South Power Station used up more water in order to augment low generation at the coal fired stations.  This situation led to a reduction of  water levels in the Lake Kariba which is available for power generation, and necessitated the reduction of the station’s generation by the ZRA to an average of 250MW, hence bringing about an increase in load shedding over the period under review.

Small thermals collectively produced 31.33GWh of energy, falling 55.45% short of the quarterly goal of 70.32GWh.  The thermal stations’ failure to attain scheduled generation levels in the fourth quarter of 2022 was caused by the incessant plant challenges and limited coal supplies which led to a reduction in power generation.

Hwange Power Station generated with an average of three units during the quarter compared to a target of five units as per the 2022 production plan, missing the quarterly energy sent out target by 34.02%. Unit 5 at Hwange is currently awaiting life extension which is expected to begin in the second quarter of 2023.

The Deka Upgradation Project is on schedule and 85% complete and on course to be completed by March 31, 2023. Current works include pipe laying and fitting, construction of the gravel access road along the pipeline and excavation of the pipeline trench.  The pipeline project is critical to enhance operationalisation of the Hwange Thermal Power Station which is being boosted with 600MW capacity under a US$1.4 Billion investment.

Construction of the new Ingagula houses is underway and being implemented in parallel to the Hwange Expansion Project.  The new residential area will also have amenities such as schools, clinics and other facilities to ensure that residents are well catered for in the new neighbourhood.

 